22. CONSTRUCTION CONTRACT AND OTHER COMMITMENTS
The following is a summary of major construction contract commitments remaining at fiscal year-end:
Project | Contract Amount | Completed to Date | Balance Committed | ||
Hudson Middle School Campus Redevelopment | $ 7,535,178 | $ 4,688,876 | $ 2,846,302 | ||
James Marlowe Elementary School Classroom Addition & Renovations | $ 6,221,536 | $ 2,792,921 | $ 3,428,615 | ||
Kirkland Ranch Academy for Innovation New School Construction | $ 46,168,556 | $ 13,216,122 | $ 32,952,434 | ||
Northwest Elementary School Campus Redevelopment | $ 12,842,627 | $ 12,179,423 | $ 663,204 | ||
Starkey Ranch K-8 New School Contruction | $ 33,734,378 | $ 28,580,629 | $ 5,153,749 | ||
Zephyrhills High School Campus Redevelopment | $ 29,087,686 | $ 24,490,444 | $ 4,597,242 | ||
Total | $ 135,589,961 | $ 85,948,415 | $ 49,641,546 |